Average Man-Loading

• Number of estimated man-hours 2,910

• Number of hours in a work day 8

• Number of work days in one month 20

• Number of months in contract 6

2910 (total hours) / 8 (hours in 1 day) = 364 work days

• It will take one man 364 days to complete the contract.

• The contract says the job shall be completed in 6 months.

• 6 (months) x 20 (work days in 1 month) = 120 contract days.

364 (days for 1 man) / 120 (contract days) = 3 men

• The average man-load will be three men.