Being even more competitive and still secure.
Actual volume to date $739,490.00
Actual overhead to date $80,000.00
$80,000.00 overhead divided by
$739,490.00 actual volume = 11%
Minimum profit at 15% risk $4,260.00
Material with sales tax $77,206.00
Labor with taxes and insurance $28,402.00
Job expense $2,863.00
Direct job costs $108,471.00
11% overhead 11,932.00
Contractor’s cost $120,864.00
Profit 4,260.00
Bid price $125,124.00