Actual overhead to date |
$80,000.00 |
|
|
Actual overhead money collected |
$93,907.00 |
|
|
Excess overhead money |
$13,607.00 |
|
|
15% overhead markup for Bid 1 |
$16,271.00 |
|
|
$16, 271.00 - $13,607.00 |
$2,664.00 |
|
|
$13,607.00 in excess overhead has been applied to $16,271.00 overhead in Bid 1. | |||
Material with sales tax |
$77,206.00 |
|
|
Labor with taxes and insurance |
$28,402.00 |
|
|
Job expense |
$2,863.00 |
|
|
Direct job costs |
$108,471.00 |
|
|
Overhead |
2,664.00 |
|
|
Contractor cost |
$111,135.00 |
|
|
5% profit |
5,557.00 |
|
|
Bid Price |
$116,692.00 |
|
|