• Number of estimated man-hours 2,910
• Number of hours in a work day 8
• Average man-load 3 men
• Number of work hours each day (3 men x 8 hours) 24
• Number of weeks in contract 25
• Man-hour breakdown:
Code |
Hours |
Work Days |
Work Weeks |
1 |
1,530 / 24 = |
67 = |
13 |
2 |
215 / 24 = |
9 = |
2 |
3 |
524 / 24 = |
22 = |
5 |
4 |
553 / 24 = |
23 = |
5 |
5 |
58 / 24 = |
3 = |
1 |
6 |
29 / 2 = |
2 = |
1 |