SITE WORK - Hand Digging
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
6" x 6" 0.00 0.00 0.01 0.01 0.01 0.02
6" x 12" 0.00 0.00 0.03 0.04 0.05 0.05
6" x 18" 0.00 0.00 0.04 0.05 0.06 0.07
6" x 24" 0.00 0.00 0.06 0.08 0.09 0.11
12" x 6" 0.00 0.00 0.03 0.04 0.05 0.05
12" x 12" 0.00 0.00 0.06 0.08 0.09 0.11
12" x 18" 0.00 0.00 0.09 0.11 0.14 0.16
SITE WORK - Trencher
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
6" x 12" 0.58 0.96 0.02 0.03 0.03 0.03
6" x 18" 0.58 0.96 0.02 0.03 0.03 0.03
6" x 24" 0.58 0.96 0.02 0.03 0.03 0.03
6" x 36" 0.84 1.40 0.02 0.03 0.03 0.03
SITE WORK - Backhoe Trenching
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
12" X 24" 2.67 4.45 0.05 0.06 0.08 0.09
12" X 36" 2.67 4.45 0.05 0.06 0.08 0.09
12" X 48" 3.12 5.20 0.06 0.08 0.09 0.11
18" X 24" 2.85 4.75 0.05 0.06 0.08 0.09
18" X 36" 3.18 5.30 0.06 0.08 0.09 0.11
18" X 48" 4.02 6.70 0.08 0.10 0.12 0.14
24" X 24" 4.26 7.10 0.06 0.08 0.09 0.11
24" X 36" 5.040 8.40 0.08 0.10 0.12 0.14
24" X 48" 5.54 9.24 0.09 0.11 0.14 0.16
30" X 48" 6.09 10.15 0.10 0.12 0.15 0.17
30" X 60" 7.65 12.75 0.12 0.15 0.18 0.21
36" X 60" 7.89 13.15 0.12 0.15 0.18 0.21
SITE WORK - Site Excavation
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Excavate Cubic Yard 10.26 17.10 0.35 0.44 0.52 0.61
Backfill Cubic Yard 20.22 33.70 0.30 0.38 0.45 0.53
SITE WORK - Concrete
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Cubic Yard of 2500# 121.50 270.00 0.40 0.50 0.60 0.70
Cubic Yard of 3000# 151.20 336.00 0.40 0.50 0.60 0.70
Cubic Yard of 4000# 175.50 390.00 0.40 0.50 0.60 0.70
MATERIAL PRICES AND LABOR UNITS FOR TRENCHING AND BACKHOE PER FOOT
MATERIAL PRICES AND LABOR UNITS FOR EXCAVATION AND CONCRETE PER CUBIC YARD