Page 217 - Electrical Price & Labor Units Guide
P. 217
05-11-20
100-3
SITE WORK - Sonotube Concrete Pole Bases
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
16" x 36" 281.40 469.00 2.00 2.50 3.00 3.50
16" x 48" 337.80 563.00 2.30 2.88 3.45 4.03
24" x 48" 446.40 744.00 3.00 3.75 4.50 5.25
24" x 60" 645.00 1,075.00 3.30 4.13 4.95 5.78
24" x 72" 667.20 1,112.00 3.60 4.50 5.40 6.30
24" x 84" 746.40 1,244.00 3.80 4.75 5.70 6.65
24" x 96" 918.00 1,530.00 4.00 5.00 6.00 7.00
30" x 84" 1,181.40 1,969.00 3.80 4.75 5.70 6.65
30" x 96" 1,245.00 2,075.00 4.00 5.00 6.00 7.00
SITE WORK - Formed Concrete Pole Bases
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Lumber Per Sq Foot 7.17 11.95 0.04 0.05 0.06 0.07
Set Small Form 0.00 0.00 1.00 1.25 1.50 1.75
Set Medium Form 0.00 0.00 2.00 2.50 3.00 3.50
Set Large Form 0.00 0.00 3.00 3.75 4.50 5.25
Remove Small Form 0.00 0.00 1.00 1.25 1.50 1.75
Remove Medium Form 0.00 0.00 1.50 1.88 2.25 2.63
Remove Large Form 0.00 0.00 2.00 2.50 3.00 3.50
SITE WORK - Anchor Bolts
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
3/8" 0.00 0.00 0.25 0.31 0.38 0.44
1/2" 0.00 0.00 0.30 0.38 0.45 0.53
3/4" 0.00 0.00 0.40 0.50 0.60 0.70
1" 0.00 0.00 0.50 0.63 0.75 0.88
MATERIAL PRICES AND LABOR UNITS ARE PER EACH
NPG AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
8-3 COPYRIGHT © 1996-2020 by ELECTRICAL RESOURCES, INC.