Page 6 - National Electrical Price Guide
P. 6
08-07-17
100-1
SITE WORK - Hand Digging
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
6" x 6" 0.00 0.00 0.01 0.01 0.01 0.02
6" x 12" 0.00 0.00 0.03 0.04 0.05 0.05
6" x 18" 0.00 0.00 0.04 0.05 0.06 0.07
6" x 24" 0.00 0.00 0.06 0.08 0.09 0.11
12" x 6" 0.00 0.00 0.03 0.04 0.05 0.05
12" x 12" 0.00 0.00 0.06 0.08 0.09 0.11
12" x 18" 0.00 0.00 0.09 0.11 0.14 0.16
SITE WORK - Trencher
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
6" x 12" 0.35 0.65 0.02 0.03 0.03 0.03
6" x 18" 0.35 0.65 0.02 0.03 0.03 0.03
6" x 24" 0.35 0.65 0.02 0.03 0.03 0.03
6" x 36" 0.50 0.90 0.02 0.03 0.03 0.03
SITE WORK - Backhoe Trenching
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
12" X 24" 1.65 2.95 0.05 0.06 0.08 0.09
12" X 36" 1.65 2.95 0.05 0.06 0.08 0.09
12" X 48" 1.90 3.45 0.06 0.08 0.09 0.11
18" X 24" 1.75 3.15 0.05 0.06 0.08 0.09
18" X 36" 1.95 3.50 0.06 0.08 0.09 0.11
18" X 48" 2.50 4.50 0.08 0.10 0.12 0.14
24" X 24" 2.60 4.70 0.06 0.08 0.09 0.11
24" X 36" 3.10 5.60 0.08 0.10 0.12 0.14
24" X 48" 3.40 6.15 0.09 0.11 0.14 0.16
30" X 48" 3.75 6.75 0.10 0.12 0.15 0.17
30" X 60" 4.70 8.50 0.12 0.15 0.18 0.21
36" X 60" 4.85 8.75 0.12 0.15 0.18 0.21
SITE WORK - Site Excavation
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Excavate Cubic Yard 6.30 11.35 0.35 0.44 0.52 0.61
Backfill Cubic Yard 12.45 22.50 0.30 0.38 0.45 0.53
SITE WORK - Concrete
Average Suggested LABOR HOURS
Description Cost Resale LOW MED HIGH X-HIGH
Cubic Yard of 2500# 95.50 171.90 0.40 0.50 0.60 0.70
Cubic Yard of 3000# 99.00 178.20 0.40 0.50 0.60 0.70
Cubic Yard of 4000# 105.00 185.00 0.40 0.50 0.60 0.70
MATERIAL PRICES AND LABOR UNITS FOR TRENCHING AND BACKHOE PER FOOT
MATERIAL PRICES AND LABOR UNITS FOR EXCAVATION AND CONCRETE PER CUBIC YARD
NPG AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA
8-1 COPYRIGHT © 1996-2017 by ELECTRICAL RESOURCES, INC.