Page 151 - Electrical Price & Labor Units Guide
P. 151
06-28-21
50-7
OCAL-BLUE PVC COATED CONDUIT HUBS - Standard
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale (0-6') (6-10') (10-15') (15-20')
1/2" HUB1/2-G 52.18 64.98 0.17 0.21 0.26 0.30
3/4" HUB3/4-G 56.29 73.83 0.19 0.23 0.28 0.33
1" HUB1-G 74.08 92.26 0.20 0.25 0.30 0.35
1-1/4" HUB11/4-G 85.18 106.08 0.25 0.31 0.38 0.44
1-1/2" HUB11/2-G 97.40 121.29 0.30 0.38 0.45 0.53
2" HUB2-G 140.16 174.55 0.35 0.44 0.53 0.61
2-1/2" HUB21/2-G 219.32 273.12 0.55 0.69 0.83 0.96
3" HUB3-G 301.13 375.01 0.65 0.81 0.98 1.14
3-1/2" HUB31/2-G 390.66 486.50 0.80 1.00 1.20 1.40
4" HUB4-G 477.67 594.86 0.95 1.19 1.43 1.66
5" HUB5-G 573.25 713.89 1.20 1.50 1.80 2.10
6" HUB6-G 680.89 847.93 1.40 1.75 2.10 2.45
OCAL-BLUE PVC COATED KNOCKOUT HUBS - Grounded
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale (0-6') (6-10') (10-15') (15-20')
1/2" STG1-G 73.11 91.05 0.17 0.21 0.23 0.30
3/4" STG2-G 76.19 94.88 0.19 0.23 0.28 0.33
1" STG3-G 81.44 101.42 0.20 0.25 0.30 0.35
1-1/4" STG4-G 89.79 111.82 0.25 0.31 0.38 0.44
1-1/2" STG5-G 127.73 159.07 0.30 0.38 0.45 0.53
2" STG6-G 160.10 199.38 0.35 0.44 0.53 0.61
2-1/2" STG7-G 236.98 295.12 0.55 0.69 0.83 0.96
3" STG8-G 307.38 382.79 0.65 0.81 0.98 1.14
3-1/2" STG9-G 403.40 502.37 0.80 1.00 1.20 1.40
4" STG10-G 503.71 627.29 0.95 1.19 1.43 1.66
5" STG11-G 654.65 815.25 1.20 1.50 1.80 2.10
6" STG12-G 745.23 928.06 1.40 1.75 2.10 2.45
OCAL-BLUE PVC COATED SPLIT COUPLINGS
Average Suggested LABOR HOURS
Description Cat. No. Cost Resale (0-6') (6-10') (10-15') (15-20')
1/2" TCC1-G 28.52 35.52 0.15 0.19 0.23 0.26
3/4" TCC2-G 29.20 36.36 0.20 0.25 0.30 0.35
1" TCC3-G 43.02 53.58 0.22 0.28 0.33 0.39
1-1/4" TCC4-G 57.82 72.00 0.25 0.31 0.38 0.44
1-1/2" TCC5-G 70.40 87.67 0.30 0.38 0.45 0.53
2" TCC6-G 148.82 185.33 0.35 0.44 0.53 0.61
2-1/2" TCC7-G 234.96 292.60 0.45 0.56 0.67 0.79
3" TCC8-G 319.20 397.51 0.60 0.75 0.90 1.05
3-1/2" TCC9-G 435.76 542.67 0.80 1.00 1.20 1.40
4" TCC10-G 535.37 666.71 1.00 1.25 1.50 1.75
5" TCC12-G 1,102.11 1,372.49 1.30 1.63 1.95 2.28
6" TCC14-G 1,475.11 1,837.00 1.65 2.06 2.48 2.89
MATERIAL PRICES AND LABOR UNITS ARE PER EACH
NPG AVERAGE COST COLUMN IS A NATIONAL AVERAGE AND SHOULD BE VERIFIED FOR YOUR AREA